Bishan,
Instead of using 21 in your last equation, use Tsetpoint where the
setpoint is an input to the equation from a forcing function which is 21
during the day and 18 at night.
Jeff
---
Jeff Thornton
President - TESS LLC
3 N. Pinckney Street, Suite 202, Madison WI USA 53703
Office: (608) 274-2577 Fax: (608) 278-1475
www.tess-inc.com
E-Mail: thornton at tess-inc.com
On 10/18/2018 11:46 am, Bishan Thapa via TRNSYS-users wrote:
> Hello everyone,
>
> I was looking to calculate hours under set point which counts the unmet hours excluding the night set back. I need to do that for first three months and last two months of year as those are only the heating periods for me.
>
> I have developed preliminary equation in equation tab.
> 2160 =end of march
> 7296 = beginning of november
> K1 = LE(time,2160)
> K2 = GE(time,7296)
> HUSP = K1*LT(temp,21) +K2*LT(temp,21)
>
> But this calculation includes the night set back temperature as well which is 18 C. How to avoid including the night set back temperature in the calculation ?
>
> Thank you
>
> Bishan Thapa
> UNCC
>
> _______________________________________________
> TRNSYS-users mailing list
> TRNSYS-users at lists.onebuilding.org
> http://lists.onebuilding.org/listinfo.cgi/trnsys-users-onebuilding.org [1]
Links:
------
[1]
http://lists.onebuilding.org/listinfo.cgi/trnsys-users-onebuilding.org
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/trnsys-users-onebuilding.org/attachments/20181018/fdfd20da/attachment.htm>
More information about the TRNSYS-users
mailing list