[Equest-users] Hot Water for Boilers with LP Gas for office building in Mexico City using eQuest 3.65

Sharad Kumar sharadcapricious at gmail.com
Mon Mar 28 04:48:34 PDT 2016


Hi Jose,

I think you are trying to configure the fuel utility rate.
One need to have a fuel utility rate (and meter) as gas for LP gas as there
can't be any measure to configure the fuel utility rate as eQUEST can't
help LP gas.

Thanks,
Sharad. Kumar.
Green Horizon Consulting LLP.
Gurgaon.


Today's Topics:

   1. Simulation of a Steel Deck + concrete for an office building
      in eQuest 3.65 (Jos? Luis Berm?dez Alcocer)
   2. Hot Water for Boilers with LP Gas for office building in
      Mexico City using eQuest 3.65 (Jos? Luis Berm?dez Alcocer)
   3. Re: Simulation of a Steel Deck + concrete for an office
      building in eQuest 3.65 (John Aulbach)


---------- Forwarded message ----------
From: "José Luis Bermúdez Alcocer" <beralco at yahoo.com.mx>
To: Equest-users <equest-users at lists.onebuilding.org>
Cc:
Date: Sun, 27 Mar 2016 03:20:36 +0000 (UTC)
Subject: [Equest-users] Hot Water for Boilers with LP Gas for office
building in Mexico City using eQuest 3.65
To whom it may concern:

The office building is located in Mexico City.  I am thinking about using a
series of boilers to heat water for the system.  (It is not an hydronic
system.)  I need to use LP Gas as the fuel.  I am checking the help command
in eQuest and the only options I have is either "gas" or electricity.  I
assume that "gas" stands for natural gas.  How can I simulate the LP Gas to
use for the boilers?  Has anybody done something similar?  Any comments
will be highly appreciated!

Kind regards,

Jose Luis Bermudez Alcocer, Ph.D., M.Arch., B.Arch.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20160328/3478e629/attachment-0002.htm>


More information about the Equest-users mailing list