Hi everyone

I am working on multifamily project where there is a single DX package unit
for each floor when I assign a package for all the floor zones I have a lot
of unmet hours except for the thermostat zone, but if I assign a package
unit for each zone I have zero unmet hours. so I am just wondering what
causing this problem?