[TRNSYS-users] Deactivate battery
David BRADLEY via TRNSYS-users
trnsys-users at lists.onebuilding.org
Fri Jul 15 07:53:49 PDT 2016
Benjamin,
Probably you have to be a little careful how you implement the
switch. If you implement a switch that is on a timer so that no matter
what, the inverter sees that there is no power available from the
renewable source at certain times of day then there should be no reason
for there to be convergence problems. However, if your switch is
watching the state of charge of the battery or something else that might
change then the switch needs to have some hysteresis in it. I don't know
what your exact situation is but pretend that the switch is watching the
battery SOC and stops charging the battery if the battery SOC gets above
0.9. If you implement this switch with a simple equation then charging
will stop when the SOC gets to 0.9000000000001 and allow charging as
soon as the SOC falls back to 0.9000000000000. You need to use one of
the thermostat controllers to provide a deadband on the SOC so that
charging stops when SOC reaches 0.90 and stops until the battery falls
back to 0.85 (or something)
The inverter/charge controller model isn't all that complicated. It
looks at a load, at the power available from renewables and at the
battery SOC and makes a decision as to how the power should flow. If
you're trying to effectively remove the battery without deleting it you
need to figure out how to make the inverter/charge controller think that
the battery should never be charged and can never provide power to the
load. You might look at some of the inverter/charge controller
parameters that set up when the battery can and cannot be charged based
on its SOC. If you set those values close to each other and start the
battery somewhere outside that range you may be able to effectively
prevent the battery from having an influence on the system.
kind regards,
David
On 07/15/2016 02:58, Manrique Delgado Benjamin via TRNSYS-users wrote:
>
> Thanks for the reply. I have used that strategy successfully with
> other Types, but unfortunately the inverter just ignores the switch. A
> message in the List file says ”The input to the listed units have not
> converged at this timestep. The values at the last iteration will be
> used and the simulation will proceed”.
>
> *From:*Ben Heymer [mailto:bheymer at gmail.com]
> *Sent:* Thursday, July 14, 2016 9:43 PM
> *To:* Manrique Delgado Benjamin <benjamin.manriquedelgado at aalto.fi>;
> TRNSYS users mailing list at OneBuilding.org
> <trnsys-users at lists.onebuilding.org>
> *Subject:* Re: [TRNSYS-users] Deactivate battery
>
> I'm not familiar with that component (Type 47a) but its usually
> possible to use equations to effectively disconnect the links to and
> from any Type.
>
> You can zero out inputs to the type with something like this:
>
> input1 = datapoint1 * switch ! (where "switch" = 1 for "on" or 0 for
> "off")
>
> You can choose to use outputs from one type or another type with
> something like this:
>
> output1 = output1a * switch + output1b * (1 - switch) ! (where
> "switch" = 1 for "on" or 0 for "off")
>
> This will take a bit of time to set up and it's not very elegant, but
> the freedom to hack is what makes TRNSYS great!
>
> On Thu, Jul 14, 2016 at 9:54 AM, Manrique Delgado Benjamin via
> TRNSYS-users <trnsys-users at lists.onebuilding.org
> <mailto:trnsys-users at lists.onebuilding.org>> wrote:
>
> Dear all,
>
> Is there a way to deactivate a battery (Type 47a) without having
> to delete it from a model? I want to do an optimization that
> includes options with and without battery, so I need to find a way
> to give the battery zero capacity or stop the inverter from
> charging/discharging it. I have tried different values for High
> and Low limit on FSOC but the inverter basically ignores them when
> the value doesn’t converge. Any suggestions?
>
> Cheers,
>
> Benjamin Manrique D.
>
> Aalto University
>
> Finland
>
>
> _______________________________________________
> TRNSYS-users mailing list
> TRNSYS-users at lists.onebuilding.org
> <mailto:TRNSYS-users at lists.onebuilding.org>
> http://lists.onebuilding.org/listinfo.cgi/trnsys-users-onebuilding.org
>
>
>
> _______________________________________________
> TRNSYS-users mailing list
> TRNSYS-users at lists.onebuilding.org
> http://lists.onebuilding.org/listinfo.cgi/trnsys-users-onebuilding.org
--
***************************
David BRADLEY
Principal
Thermal Energy Systems Specialists, LLC
22 North Carroll Street - suite 370
Madison, WI 53703 USA
P:+1.608.274.2577
F:+1.608.278.1475
d.bradley at tess-inc.com
http://www.tess-inc.com
http://www.trnsys.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/trnsys-users-onebuilding.org/attachments/20160715/917c2295/attachment-0003.htm>
More information about the TRNSYS-users
mailing list