[TRNSYS-users] prebid floors

David Bradley bradley at tess-inc.com
Tue Jul 6 05:45:53 PDT 2004


Dear Vincent,
   The layers that separate one floor from the next are an ADJACENT wall as 
opposed to an EXTERIOR or a BOUNDARY wall. Once you create the wall that 
will serve as the floor of one zone and the ceiling of another and select 
ADJACENT from the pull down menu, Prebid will then ask you to specify the 
zone that is on the other side of the floor. Recall also that if I am not 
mistaken, ADJACENT walls are specified with the "front" of the wall in the 
zone where you are working and the "back" of the wall in the adjacent zone. 
If you have defined your floor in the opposite order, Prebid provides you 
with a radio button that allows you to flip the wall around and specify 
that the "back" of the wall is in the active zone.
Kind regards,
   David

At 04:11 PM 7/5/2004 +0200, Vincent CORNILLON wrote:
>Dear TRNSYS users
>
>I have one question about prebid. I'm modelling a building with 3 floors.
>How can I link floors with each others?
>
>thank you for your help
>
>Vincent Cornillon
>
>
>_______________________________________________
>TRNSYS-users mailing list
>TRNSYS-users at engr.wisc.edu
>https://www.cae.wisc.edu/mailman/listinfo/trnsys-users

****************************************************************************************
Thermal Energy System Specialists (TESS), LLC
David BRADLEY                           2916 Marketplace Drive - Suite 104
Partner                                        Madison, WI 53719
Phone: (608) 274-2577 USA
Fax: (608) 278-1475
E-mail: bradley at tess-inc.com
Web Pages:  http://www.tess-inc.com     and      http://www.trnsys.com

"Providing software solutions for today's energy engineering projects"
****************************************************************************************





More information about the TRNSYS-users mailing list