Hi,
As per my understanding you have created the E1d shell after E2 shell.
That's why the drop down list is not showing the E1d. Equest will allow
this option when E2 created after Ed1 in wizard mode.
Thanks
On Jun 24, 2015 1:32 AM, <equest-users-request at lists.onebuilding.org> wrote:
> Send Equest-users mailing list submissions to
> equest-users at lists.onebuilding.org
>
> To subscribe or unsubscribe via the World Wide Web, visit
>
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
>
> or, via email, send a message with subject or body 'help' to
> equest-users-request at lists.onebuilding.org
>
> You can reach the person managing the list at
> equest-users-owner at lists.onebuilding.org
>
> When replying, please edit your Subject line so it is more specific
> than "Re: Contents of Equest-users digest..."
>
> Today's Topics:
>
> 1. SD Bldg Shell -Change in bldg shell order
> (Pranita Kothuru Komirishetty)
>
>
> ---------- Forwarded message ----------
> From: Pranita Kothuru Komirishetty <pranita.kothuru at gmail.com>
> To: equest-users <equest-users at lists.onebuilding.org>
> Cc:
> Date: Tue, 23 Jun 2015 10:57:22 -0400
> Subject: [Equest-users] SD Bldg Shell -Change in bldg shell order
> Hello All -
>
> I am working on a multistory building with 15 floor types (E1 to E15).
> After doing all the 15 shell types we have decided to split the E1 into 5
> different shells (E1, E1a, E1b, E1c, E1d) since the zoning is very
> different on each of these floors.
>
> I was able to create new shells( by copying data from E1) and place them
> above the corresponding floor. I am having issues when it comes to placing
> my E2 above E1d.
>
> In the schematic design wizard screen 1, in Posiiton this shell
> immediately above............... (where we have to pick the shell from the
> drop down list), here I do not see the E1d shell (which I created after all
> the above above shells were created.
>
> I changed the prefix names to E1a to E1d instead of using the default
> eQuest names.
>
> Currently E2 says its above E1, instead it has to be above E1d. The drop
> down list does not show E1d. I saved and simulated the model assuming it
> might then populate the new shells in the drop down list. This did not work.
>
> Any thoughts on how to fix this.
>
>
> --
>
> *- Pranita *
>
>
> _______________________________________________
> Equest-users mailing list
> Equest-users at lists.onebuilding.org
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20150624/5459ca7d/attachment-0005.htm>
More information about the Equest-users
mailing list