[Equest-users] FW: Solar panels

David Eldridge dse at grummanbutkus.com
Wed Nov 24 11:13:18 PST 2010


My LEED-NC v2.2 Reference Guide p188 says “On-Site Renewable Energy and
Site-Recovered Energy costs are not included in the Proposed Building
Performance (this is a LEED for New Construction exception to ASHRAE
Standard 90.1 G2.4); therefore, these systems receive full credit using the
PRM”…examples include PV…



p264 of the BD+C 2009 Reference Guide has a similar note about using
harvested free energy for EAC1 performance.



As far as CIRs I’m not sure, but LEED has always been pretty clear that you
count on-site renewable energy production for both EAC1 and EAC2.



David

*
*



*David S. Eldridge, Jr.**, P**.**E**.**, LEED AP BD+C, BEMP, HBDP*

Project Manager



Direct: (847) 316-9224 | Fax: (847) 328-4550

http://www.grummanbutkus.com



*Grumman/Butkus Associates* | 820 Davis Street, Suite 300 | Evanston, IL
60201

Energy Efficiency Consultants and Sustainable Design Engineers

*
*



*
*



David S. Eldridge, Jr., P.E., LEED AP BD+C, BEMP, HBDP

*Grumman/Butkus Associates*

*
*



*From:* equest-users-bounces at lists.onebuilding.org [mailto:
equest-users-bounces at lists.onebuilding.org] *On Behalf Of *Alan Crittendon
*Sent:* Wednesday, November 24, 2010 12:07 PM
*To:* equest-users at lists.onebuilding.org
*Subject:* [Equest-users] FW: Solar panels



I sent this yesterday but have a couple more things to add:



1)  how does LEED deal with solar power and does Section G2.4 ASHRAE
90.1-2007 just mean that you can't take credit for the utility buying back
the extra energy or cant model at all?

2)  Has there been any CIRs that discuss solar PV from LEED?



Alan Crittendon, PE, LEED AP
DW Collier Engineering, Inc.
------------------------------

*From:* Alan Crittendon [mailto:alanc at dwcei.com]
*Sent:* Tuesday, November 23, 2010 1:28 PM
*To:* 'equest-users at lists.onebuilding.org'
*Subject:* Solar panels



Does ASHRAE 90.1 allow the use of solar panels when calculating the proposed
bldg?  if so how do you model them?



Alan Crittendon, PE, LEED AP
DW Collier Engineering, Inc.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20101124/52d127c7/attachment.htm>


More information about the Equest-users mailing list