I wanted to run something by everyone to see if this is how most people
model underground walls:            

 

For my climate zone (4A), the required C-factor for Underground Wall is
1.140 (no U-value listed).

 

If you go to Appendix A of 90.1-2004, specifically sections A4.1 and
Table A4.2, I *think* that you come to the conclusion that the baseline
underground walls should be modeled as 8 inch medium weight concrete
block with a density of 115 lb/ft3, solid grouted cores, and NO
INSULATION.  This is what A4.1 says, and the published C-factors in
Table A4.2 indicate that a C-factor of 1.140 is obtained using this wall
and no framing / no insulation.

 

If you then refer to Table A3.1C, for that wall type, sure enough a
C-factor of 1.140 is listed with a corresponding U-value of 0.58.

 

When I run my baseline model with an underground wall construction
having a U-value of 0.58, I end up with way more cooling hours and
energy that my proposed model, which has R-13 insulation.  This is
presumably because those underground spaces are constantly losing heat
thru the poor wall construction to the 55 degree earth heat sink (or
whatever eQuest calculates it as).

 

I'm not complaining, as it makes the proposed system look that much more
efficient, but I just wanted to double check that I'm doing this right.

 

On a side note, I'm having a tough time reducing my unmet load hours for
the underground VAV system, but that's besides the point...

 

Thanks!

 

GHT Limited
James Hansen, PE, LEED AP

Senior Associate

1010 N. Glebe Rd, Suite 200

Arlington, VA  22201-4749

703-338-5754 (Cell)

703-243-1200 (Office)

703-276-1376 (Fax)

www.ghtltd.com <http://www.ghtltd.com/> 

 

 


The information contained in this communication is confidential, may be privileged, and is intended only for the use of the addressee.  It is the property of GHT Limited.  Unauthorized use, disclosure or copying of this communication or any part thereof is strictly prohibited and may be unlawful.  If you have received this communication in error, please notify me immediately by return e-mail or by e-mail to ght at ghtltd.com, and destroy this communication and all copies thereof, including all attachments.  Thank you.



-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20100330/96a83996/attachment.htm>


More information about the Bldg-sim mailing list