Check the PS-E and PS-F reports. These have the master meters and
sub-meters broken out by month. I will sometimes create an additional
utility meter to avoid confusing the LEED review team when they look at the
BEPS reports. Of course this may throw off any block type or demand type
utility rates.
Thomas Serra
Project Manager
EMO Energy Solutions, LLC
3141 Fairview Park Drive, Suite 450
Falls Church, VA 22042
voice 703-205-0445 ex-113
fax 703-205-0449
From: Seun Odukomaiya [mailto:SOdukomaiya at lacquis.com]
Sent: Wednesday, March 31, 2010 9:15 AM
To: equest-users at lists.onebuilding.org
Subject: [Equest-users] SubMeters in Equest
Equest users,
In order to isolate my elevator energy usage for a LEED model, I created a
submeter of type electric and assigned the elevator loads to it. I then
assigned that submeter to the main electric meter. This seems to have worked
just fine. My question then is this: Which report details the energy
consumption of my submeter. I looked at the BEPS and BEPU reports, but they
have the total electric usage listed without my submeter broken out. Am I
looking at the right report? Thanks
Seun Odukomaiya, LEED AP - Mechanical Engineer
L'Acquis Consulting Engineers
9229 Delegates Row, Suite 550
Indianapolis, IN 46240
voice: (317) 706-2075 Ext. 255
fax: (317) 706-2076
email: sodukomaiya at laceindy.com
web: www.laceindy.com <http://www.laceindy.com/>
P Please consider the environment before printing this e-mail.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100402/5c05d80d/attachment.htm>
More information about the Equest-users
mailing list