    Bachchulal,<br>
      Type94 (and Type194) compute two power outputs. The first is the
    power at the maximum power point. The second is the power at a
    user-defined load voltage. The load voltage is an input to the model
    so if you have not hooked up a load voltage to the PV model then
    probably the load voltage is 0 and thus the power is zero. If your
    PV is using a max power point tracker (and almost all of them do)
    then you can simply use the output for the power at the maximum
    power point.<br>
    Kind regards,<br>
     David<br>
    <br>
    <br>
    <br>
    <div class="moz-cite-prefix">On 5/20/2014 22:26, Bachchulal Gupta
      wrote:<br>
    </div>
    <blockquote
cite="mid:CAH81WQDqGN-2qzBNCUDftteuA-d=KjUvDq_Un9dB0i_eNhPF2w@mail.gmail.com"
      type="cite">
      <div dir="ltr">
        <div>
          <div>dear all <br>
          </div>
          i am simulating a five zone building, air conditioning by a
          packaged A.c,operated by photovoltaic. the temperature of all
          zones are well maintained in the  desired schedule but my
          problem is that the output of PV has two option 1. Array power
          2. Power at maximum power point tracker <br>
        </div>
        <div>here the array power is all times given as ZERO while power
          at MPPT has value but i think in real that may not used . <br>
        </div>
        <div>any one can help why this problem occurs i am attaching the
          model <br>
          <br>
        </div>
        <div>regards <br>
          <br>
        </div>
        <div>B.L.Gupta <br>
        </div>
        <div><br>
        </div>
      </div>
      <br>
      <fieldset class="mimeAttachmentHeader"></fieldset>
      <br>
      <pre wrap="">_______________________________________________
TRNSYS-users mailing list
<a class="moz-txt-link-abbreviated" href="mailto:TRNSYS-users@cae.wisc.edu">TRNSYS-users@cae.wisc.edu</a>
<a class="moz-txt-link-freetext" href="https://mailman.cae.wisc.edu/listinfo/trnsys-users">https://mailman.cae.wisc.edu/listinfo/trnsys-users</a>
</pre>
    </blockquote>
    <br>
    <pre class="moz-signature" cols="72">-- 
***************************
David BRADLEY
Principal
Thermal Energy Systems Specialists, LLC
22 North Carroll Street - suite 370
Madison, WI  53703 USA

P:+1.608.274.2577
F:+1.608.278.1475
<a class="moz-txt-link-abbreviated" href="mailto:d.bradley@tess-inc.com">d.bradley@tess-inc.com</a>

<a class="moz-txt-link-freetext" href="http://www.tess-inc.com">http://www.tess-inc.com</a>
<a class="moz-txt-link-freetext" href="http://www.trnsys.com">http://www.trnsys.com</a></pre>
  </body>
</html>