Dear All<br><br>I have a question for calculation of cooling TR for a building in eQUEST.<br><br>I run the simulation by making chiller Autosized.<br><br>After Simulation in SIM files I got following results.<br>1. PS-D Circulation loop load on Chilled water loop is 8436kBtu/Hr ~ 703TR<br>
2. PV-A Plant design parameter Chilled Water Loop 6.023 MBtu/Hr ~ 213TR<br>3. SS-D Maximum Cooling load is 8466 kBtu/Hr ~ 705TR<br><br>Which report gives actual TR for building and why PS-D and PV-A report shows different TR for same Chilled water loop.<br>
<br clear="all"><br>-- <br>With Thanks and Regards,<br>Praveen K. Jain<br>Roorkee<br>