<br><font size=2 face="sans-serif">Dear All,</font>
<br>
<br><font size=2 face="sans-serif">Refer the following data. </font>
<br>
<br><font size=2 face="sans-serif">A manufacturing building has the
following area</font>
<br>
<br><font size=2 face="sans-serif">Common area,office area
= 22% of the building area which
contribute 13% of a/c requirement</font>
<br><font size=2 face="sans-serif">Manufacturing area (clean room++)
= 57% of the building
area which contribute 87% of a/c requirement</font>
<br><font size=2 face="sans-serif">Un air-conditioned area
= 21% of the building
area.</font>
<br>
<br><font size=2 face="sans-serif">Now this building needs LEED Certification.
</font>
<br>
<br><font size=2 face="sans-serif"> To achieve EA Credit1, whether
the clean room load(process) needs to be considered in baseline design
during modelling? or only we need to consider the common area+office area+Unconditioned
area.</font>
<br>
<br><font size=2 face="sans-serif">Advance thanks for your valuable feedback.</font>