[Equest-users] equest: occupancy schedule in Airport

Nicholas Caton Nicholas.Caton at se.com
Thu Mar 14 09:27:09 PDT 2019


Not to be difficult, but one doesn’t need to look very far back in the news cycle to see that it *only* takes a federal shutdown to back up airports so badly that yeah, probably every space ends up at/beyond designed peak occupancy at the same time.

I’m bringing up this to illustrate that you need to bound and explain for yourself (first) what you are trying to get out of this building energy simulation.  Is this a historically calibrated to bills model or a future projection?  For an existing building or new construction?  Are the model outputs leveraged to put a certification/plaque on the wall or to construct an energy savings performance contract guarantee?

The most “ideal” set of schedules I can imagine would be built not on occupancy rates alone, but instead upon a trended record of (calibrated) return air CO2 sensor readings at the same or a substantially similar airport, for multiple systems/spaces.  This data would be interpreted by the modeler after seeking a detailed understanding of how (for *your* building vs the measured case) the outputs of those sensors will be actually sequenced/commissioned to determine and deliver the outside air flow as designed.  THEN you would factor your schedules up/down to consider the relative contextual variables (like projected passenger loads, city population, etc) appropriate to the purpose of your model…

… but that’s going down a path that is probably a step too far for most building energy models.  If it’s just for LEED or code compliance you quite likely could just make something up.  Just depends on the AHJ/reviewers that may be involved (asking your AHJ ahead of your own deadlines is never an expressly *bad* idea, by the way).  You might also, or minimally, want to do a cursory literature review to found your own assumptions on (i.e. google “airport occupancy rates model”).  You can rest assured that other energy modelers have tackled airports and these specific questions before – with some luck you’ll find someone proud enough of their work (or otherwise funded/paid, or tied to the pursuit of a post-graduate degree) to share their findings in publication.

I’m sorry this isn’t much more specific – I have not modeled an airport yet, specifically… but I hope this perspective helps you to define and arrive at your finish line!

~Nick


[cid:image001.png at 01D4DA4F.B526D6C0]
Nick Caton, P.E., BEMP
  Senior Energy Engineer
  Regional Energy Engineering Manager
  Energy and Sustainability Services
  Schneider Electric

D  913.564.6361
M  785.410.3317
F  913.564.6380
E  nicholas.caton at schneider-electric.com<mailto:nicholas.caton at schneider-electric.com>

15200 Santa Fe Trail Drive
Suite 204
Lenexa, KS 66219
United States

[cid:image002.png at 01D4DA4F.B526D6C0]



From: Equest-users <equest-users-bounces at lists.onebuilding.org> On Behalf Of John Aulbach via Equest-users
Sent: Wednesday, March 13, 2019 10:21 AM
To: equest-users at lists.onebuilding.org; Konstantina Kalliakoudi <kalliakoudi.k at gmail.com>
Subject: Re: [Equest-users] equest: occupancy schedule in Airport


[External email: Use caution with links and attachments]

________________________________


Lonstatina:

If you finally get your model to the Detail Edit mode, you can input a different schedule for each space. I don't think the Wizard modes will allow that.

THEN you can give each space a different people, light, equip schedule.

Try that.

John R. Aulbach
REALLY retired eQuest Guy

On Wednesday, March 13, 2019, 5:33:14 AM PDT, Konstantina Kalliakoudi via Equest-users <equest-users at lists.onebuilding.org<mailto:equest-users at lists.onebuilding.org>> wrote:


Dear all,
I have following issue
I am modeling a terminal airport in equest.
I have entered the maximum number of people in each space and I want to modify the schedules.
The situation is following:
The schedules vary significant at each month.
Each space has a different day time where the peak number of people occur. This happens because the passenger are continiously moving from each space to another, for example from check in to the boarding gates.
Each space has it's own AHU with a minimum Ooutside Air Control Method: DCV Return Sensor

My questions are following:
1)  Τhe number of people affect the energy consumption of each AHU. Each zone will NOT  simultaneously
have the maximum number of people (peak). How can I enter this time differnece. Most each zone has each own schedule?

Thank you
Konstantina K.
Mechanical Engineer




_______________________________________________
Equest-users mailing list
http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org<https://emea01.safelinks.protection.outlook.com/?url=http%3A%2F%2Flists.onebuilding.org%2Flistinfo.cgi%2Fequest-users-onebuilding.org&data=02%7C01%7CNicholas.Caton%40se.com%7C79fb54805eab449871e508d6a7c78c62%7C6e51e1adc54b4b39b5980ffe9ae68fef%7C0%7C0%7C636880872828279724&sdata=nA02miXbYW6E03eGXuyGRBqjOt0D%2BH%2F1eukAqTTazC0%3D&reserved=0>
To unsubscribe from this mailing list send  a blank message to EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG<mailto:EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG>

______________________________________________________________________
This email has been scanned by the Symantec Email Security.cloud service.
______________________________________________________________________
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20190314/1304e82c/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 255 bytes
Desc: image001.png
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20190314/1304e82c/attachment-0006.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 8477 bytes
Desc: image002.png
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20190314/1304e82c/attachment-0007.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: oledata.mso
Type: application/octet-stream
Size: 7118 bytes
Desc: oledata.mso
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20190314/1304e82c/attachment-0003.obj>


More information about the Equest-users mailing list