I have modeled PV in eQuest and had the same problem.  The simulation showed much less than the PV vendor estimated.  The actual generation history confirmed that the vendor's calculations were very close.
I have tried the TMY2 and TMY3 files for the area and it made no appreciable difference.  I requested all the information eQuest requested from the vendor and plugged that in, so it is not an input error. I even tried changing the orientation and angle of the PV panels, but could not approach the actual generation.

Maybe someone else can enlighten us? Paul Diglio

      From: Pramod .D via Equest-users <equest-users at lists.onebuilding.org>
 To: "equest-users at lists.onebuilding.org" <equest-users at lists.onebuilding.org> 
 Sent: Monday, September 3, 2018 1:03 AM
 Subject: [Equest-users] PV simulation helioscope vs eQuest
   
 <!--#yiv8945490297 _filtered #yiv8945490297 {font-family:"Cambria Math";panose-1:2 4 5 3 5 4 6 3 2 4;} _filtered #yiv8945490297 {font-family:Calibri;panose-1:2 15 5 2 2 2 4 3 2 4;}#yiv8945490297 #yiv8945490297 p.yiv8945490297MsoNormal, #yiv8945490297 li.yiv8945490297MsoNormal, #yiv8945490297 div.yiv8945490297MsoNormal {margin:0in;margin-bottom:.0001pt;font-size:11.0pt;font-family:"Calibri", sans-serif;}#yiv8945490297 a:link, #yiv8945490297 span.yiv8945490297MsoHyperlink {color:#0563C1;text-decoration:underline;}#yiv8945490297 a:visited, #yiv8945490297 span.yiv8945490297MsoHyperlinkFollowed {color:#954F72;text-decoration:underline;}#yiv8945490297 span.yiv8945490297EmailStyle17 {font-family:"Calibri", sans-serif;color:windowtext;}#yiv8945490297 .yiv8945490297MsoChpDefault {font-family:"Calibri", sans-serif;} _filtered #yiv8945490297 {margin:1.0in 1.0in 1.0in 1.0in;}#yiv8945490297 div.yiv8945490297WordSection1 {}-->Dear eQuesters,    Recently I have been working on a project where the clients are planning to use the PV modules for electricity generation. I have a Helioscope simulation report provided by the PV contractor which shows the power generation as 105,300 kWh per year. However, when I use the same details mentioned in the report for my eQuest simulation, I am getting 26,576 kWh. Can anyone please explain the discrepancies on these reports or am I missing something?    The PV system used in this project has 4 inverters of capacity 20kW each. Four segments PV models with 33.6kW, 18.6kW 16.8kW and 16.1kW power generation capacity. Tracking volts of inverters : 244-529 Vac.    I really appreciate your time.    Thanks, Pramod D. | Mechanical Engineer d.pramod at setty.com    _______________________________________________
Equest-users mailing list
http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
To unsubscribe from this mailing list send  a blank message to EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG


   
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20180903/8c22b0fc/attachment-0002.htm>


More information about the Equest-users mailing list