Just to address something mentioned in the initial prompt:  using parent "minimum humidity" as a workaround to distinguish zone inputs is clever from a MacGyver perspective, but could be clunky/inflexible when you have actual humidity setpoints to maintain someday.

Using David's example as a probably-not-so-contextually-appropriate launch pad for an example, this illustrates an alternative allowing you to define an exhaust rate per zone based upon the parent system's order in the INP (component tree):

switch(#SV(#PS()))
  case 1: (#LR("SPACE","AREA"))/4 $The 1st SYSTEM
  case 2: (#LR("SPACE","AREA"))/2 $The 2nd SYSTEM
  case 3: (#LR("SPACE","AREA"))   $The 3rd SYSTEM
  case 4: (#LR("SPACE","AREA"))/2 $etcetera
  default: no_def
endswitch

Full kudos to Mr. Bill below, who clued me into that trick.

Also worth noting: #SV(#PS()) has a related cousin #SV(#LS()), which returns the "list position" of the local component (i.e. a ZONE for a zonal input) instead of the parent (i.e. a SYSTEM for a zonal input).  The reference manual also touches on #P2S() for grandparents and ??? (I'm guessing #P3S) for great-grandparents but I haven't had cause to trial this just yet, to assert those work.

The other major method I'm aware of for distinguishing SYSTEMS within ZONE expressions involved using the SYSTEM name string, which is nicer for self-documentation (human readability) in the expression, but can introduce inflexibilities with wanting to re-name your systems down the line... I think that approach is findable the archives but can detail if requested.

~Nick

[cid:image004.png at 01D35CA0.99E8CD10]
Nick Caton, P.E., BEMP
  Senior Energy Engineer
  Regional Energy Engineering Manager
  Energy and Sustainability Services
  Schneider Electric

D  913.564.6361
M  785.410.3317
F  913.564.6380
E  nicholas.caton at schneider-electric.com<mailto:nicholas.caton at schneider-electric.com>

15200 Santa Fe Trail Drive
Suite 204
Lenexa, KS 66219
United States

[cid:image005.png at 01D35CA0.99E8CD10]



From: Equest-users [mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of David Griffin II via Equest-users
Sent: Monday, November 13, 2017 4:41 PM
To: Jennings, Coles <Coles.Jennings at MasonandHanger.com>; Bishop, Bill <bbishop at pathfinder-ea.com>; equest-users at onebuilding.org
Subject: Re: [Equest-users] Advanced Scripting/Custom Default Question - Change Space Property based on System?

I have used the BDL code below to reference the SPACE input indicated to control a ZONE input for Exhaust Air. You could code the 'Activity Description' for the AHU served by it. Just a thought.

switch(#LR("SPACE","C-ACTIVITY-DESC"))

CASE "Rest": (#LR("SPACE","AREA"))/4
CASE "Break": (#LR("SPACE","AREA"))/2
CASE "REle": (#LR("SPACE","AREA"))
CASE "Elec": (#LR("SPACE","AREA"))/2
CASE "Jani": (#LR("SPACE","AREA"))/2
CASE "Mech": (#LR("SPACE","AREA"))/2
default: no_def
endswitch

[ARCH | NEXUS]<http://www.archnexus.com>



DAVID W. GRIFFIN II

BEMP
ENERGY ANALYST

2505 E Parleys Way
Salt Lake City, UT 84109

Office 801.924.5028

archnexus.com<http://www.archnexus.com>

[Twitter]<https://twitter.com/arch_nexus>[Facebook]<https://www.facebook.com/pages/Architectural-Nexus/179588705397563?ref=ts&fref=ts>[Youtube]<https://www.youtube.com/channel/UCYRPWKF-yp-AUiI8ia2XfKw?feature=mhee>[LinkedIn]<https://www.linkedin.com/company/architectural-nexus>



From: Jennings, Coles [mailto:Coles.Jennings at MasonandHanger.com]
Sent: Monday, November 13, 2017 9:03 AM
To: Bishop, Bill; equest-users at onebuilding.org<mailto:equest-users at onebuilding.org>
Subject: Re: [Equest-users] Advanced Scripting/Custom Default Question - Change Space Property based on System?

Thanks Bill, that makes sense. Unfortunately there is no clean relationship between floors and systems, but I think adding a system number prefix to the space description as you suggest will still provide some time savings. Very much appreciate your feedback.



Coles Jennings PE, BEMP, LEED AP BD+C
Sr. Energy Engineer, Building Sciences Manager | Mason & Hanger
A Day & Zimmermann Company
D 804.521.7045 | O 804.285.4171 | F 804.217.8520
4880 Sadler Road, Suite 300 | Glen Allen, VA 23060
Mason & Hanger<http://www.masonandhanger.com/>
We do what we say.(r)


From: Bishop, Bill [mailto:bbishop at pathfinder-ea.com]
Sent: Monday, November 13, 2017 10:58 AM
To: Jennings, Coles <Coles.Jennings at MasonandHanger.com<mailto:Coles.Jennings at MasonandHanger.com>>; equest-users at onebuilding.org<mailto:equest-users at onebuilding.org>
Subject: [EXTERNAL] RE: Advanced Scripting/Custom Default Question - Change Space Property based on System?

Hi Coles,
Spaces are defined in the BDL before systems and zones. Systems are neither parents nor children of spaces, so there is no way for spaces to reference them.
You could reference the floors of the spaces if there is a relationship of systems to floors.
What you could do is include the name of the system in the space description (C-ACTIVITY-DESC) and then reference the space description with a SWITCH statement.
Regards,
~Bill

William Bishop, PE, BEMP, BEAP, CEM, LEED AP | Pathfinder Engineers & Architects LLP
Senior Energy Engineer

[cid:image006.jpg at 01D35CA0.99E8CD10]  [cid:image007.jpg at 01D35CA0.99E8CD10]



134 South Fitzhugh Street                 Rochester, NY 14608

T: (585) 698-1956                        F: (585) 325-6005

bbishop at pathfinder-ea.com<mailto:wbishop at pathfinder-ea.com>             www.pathfinder-ea.com<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.pathfinder-2Dea.com_&d=DwMFAg&c=xB5UQg5qXm2axe_t44neldV-XNditz6D2ZXZLA0vHlE&r=JrIPsTq2z-_669uhqn51VqSZFL7dpX6NqxKBTKpeQZ9m5XksAJHnQhCI_rEcbMFG&m=TPsuZzXb-d5_oj4vRDGXNr4Cblc5UDBybdEMWc2uwqQ&s=Ne5ZL4_R7KA8Un8Gr9yDAMK13olbWcBrcz3BBi-1iKw&e=>

[http://png-5.findicons.com/files/icons/977/rrze/720/globe.png]Carbon Fee and Dividend - simple, effective, and market-based.


From: Equest-users [mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of Jennings, Coles via Equest-users
Sent: Sunday, November 12, 2017 8:28 PM
To: equest-users at onebuilding.org<mailto:equest-users at onebuilding.org>
Subject: [Equest-users] Advanced Scripting/Custom Default Question - Change Space Property based on System?

Hello all,

I'm modeling a hospital building with some areas that are 24/7 and others that are on a typical 8-5 M-F schedule. There are numerous AHUs and each AHU operates on one of these two schedules. What I'd like to do is write a default script that sets the space interior load schedules (lighting, occupancy, equipment) based on which AHU that space's thermal zone is assigned to.

I often use the trick of assigning a unique min. humidity ratio for each system in a model and then writing a switch() script to change zone properties, but I am having trouble figuring out the syntax to use this trick to change space properties. There's something in the BDL hierarchy that I'm not getting.

Has anyone had success with this before?

Thanks,

Coles Jennings PE, BEMP, LEED AP BD+C
Sr. Energy Engineer, Building Sciences Manager | Mason & Hanger
A Day & Zimmermann Company
D 804.521.7045 | O 804.285.4171 | F 804.217.8520
4880 Sadler Road, Suite 300 | Glen Allen, VA 23060
Mason & Hanger<http://www.masonandhanger.com/>
We do what we say.(r)



______________________________________________________________________
This email has been scanned by the Symantec Email Security.cloud service.
______________________________________________________________________
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20171113/e20ff45f/attachment-0002.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image004.png
Type: image/png
Size: 255 bytes
Desc: image004.png
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20171113/e20ff45f/attachment-0012.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image005.png
Type: image/png
Size: 8477 bytes
Desc: image005.png
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20171113/e20ff45f/attachment-0013.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image006.jpg
Type: image/jpeg
Size: 1242 bytes
Desc: image006.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20171113/e20ff45f/attachment-0008.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image007.jpg
Type: image/jpeg
Size: 1308 bytes
Desc: image007.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20171113/e20ff45f/attachment-0009.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image008.png
Type: image/png
Size: 2842 bytes
Desc: image008.png
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20171113/e20ff45f/attachment-0014.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: oledata.mso
Type: application/octet-stream
Size: 7125 bytes
Desc: oledata.mso
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20171113/e20ff45f/attachment-0004.obj>


More information about the Equest-users mailing list