Hi All,
A 50,000 sf building we are looking at has electric DX cooling and electric heat VAV terminal boxes in the zones. The only gas use in this system is for a small pre-heat coil on the RTU and there is also an energy recovery ventilator. In developing the Baseline model, should we use System 5 (gas boiler) or go with System 6 (all electric)?
With gas, I know the default is to use Sys 5 but in this case the pre-heat is a very small part of the system so the "predominant" heating energy use is electric. The Baseline will still be modeled with the same gas pre-heater per Appendix G, either way.
Many thanks for your thoughts.
Regards,
Jeff Ross-Bain, PE, LEED Fellow
President
404-220-8955
www.rbgb.com<http://www.rbgb.com/>
Build Green. Save Time. Save Money.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20161018/e6cb31e8/attachment-0005.htm>
More information about the Equest-users
mailing list