[Equest-users] LEED Modeling
Daniel Knapp
danielk at arborus.ca
Wed Sep 23 10:47:10 PDT 2015
Since bus charging stations do not appear in ASHRAE 90.1, they are not regulated (i.e. not regulated by 90.1) and therefore fall under other/process loads.
Cheers,
Dan
—
Daniel Knapp, PhD, PPhys, LEED® AP O+M
danielk at arborus.ca
Arborus Consulting
Energy Strategies for the Built Environment
www.arborus.ca
76 Chamberlain Avenue
Ottawa, ON, K1S 1V9
Phone: (613) 234-7178 ext. 113
Fax: (613) 234-0740
> On Sep 23, 2015, at 1:27 PM, Matthew J. Baron <mbaron at wendelcompanies.com> wrote:
>
> This is more of a question on LEED as opposed to how to model it in equest. I am working on a large bus maintenance facility with internal bus storage. The client wants to install bus charging stations in the parking/storage portion of the building. Would this classify as a process load or regulated load for LEED? My thought for modeling this would be simply to determine a kw load and add it to the electric meter scheduled to run overnight. Thanks in advance.
>
> Thank you,
> Matthew J. Baron, PE
>
>
> <image002.png>
>
>
>
> Wendel, Centerpointe Corporate Park, 375 Essjay Road, Suite 200, Williamsville, NY 14221 <image003.jpg>
> p. 716.688.0766 tf. 877.293.6335 e. mbaron at wendelcompanies.com w. wendelcompanies. com
>
> ARCHITECTURE | ENGINEERING | PLANNING | ENERGY EFFICIENCY | CONSTRUCTION MANAGEMENT
>
> CONFIDENTIALITY NOTICE: This email transmission is confidential and is intended only for the person(s) named above. Its contents may also be protected by privilege, and all rights to privilege are expressly claimed and not waived. Any unlicensed distribution, copying or disclosure of this email is strictly prohibited.
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send a blank message to EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
More information about the Equest-users
mailing list