[Equest-users] Daylit areas

Fakeha Sehar fakeha_s at yahoo.com
Tue Dec 15 13:23:03 PST 2015


I have modeled DOE reference medium sized office building in eQuest. When I install photosensors, the software says that the installation is as per California Title 24,2008 standard but I observe that the installation is not as per the standard. The whole perimeter zone is considered daylit. One photosensor is installed in this zone to control daylit area which is greater than the primary daylit area(i.e. 1 window head height). Shouldn't there be two sensors to separately control primary and secondary daylit areas?

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20151215/304a7223/attachment-0001.htm>


More information about the Equest-users mailing list