I had something similar to this but had slab heating tied to the hw loop along with coils -both at different temps, followed with a portion of the building tied to a chilled water loop.
I got it to run, but didn't trust the outcome unfortunately, so we changed and simplified our system.
Eric Hethcoat, P.E.
Latimer, Sommers & Assoc., P.A.
3639 SW Summerfield Dr.
Topeka, KS. 66614
c. 913.481.3256
p. 785.233.3232
f. 785.233.0647
ehethcoat at lsapa.com
On Sep 15, 2011, at 4:34 PM, "Alex Blue" <ablue at sustainable-solutions.ca> wrote:
> The building design is that I have one chiller connected to the hot water loop, one chiller connected to the condenser loop. Then the condenser and hot water loops have a heat exchanger between them.
>
>
>
> Right now I have it modelled as two chillers, both with heat recovery to the hot water loop and both connected to the condenser loop.
>
>
>
> Does that make sense, or is there a better way to model it?
>
>
>
> This is my first eQuest project (I’ve used DOE2.1E/EE4 before.) Picked a nice complex arena to start with.
>
>
>
> Thanks,
>
> Alex
>
>
>
> <image002.jpg>
>
>
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send a blank message to EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20110915/53936967/attachment.htm>
More information about the Equest-users
mailing list