[Equest-users] Different operation schedules for ventilation system
Nick Caton
ncaton at smithboucher.com
Wed Oct 13 06:40:09 PDT 2010
Schedules generally should be identical between baseline and proposed -
if you modify one you should modify the other in the same fashion.
What is your justification to do something different? 90.1 has
provisions to alter schedules when necessary to demonstrate nonstandard
energy efficiency measures - see Table G3.1.4.
~nick
NICK CATON, E.I.T.
PROJECT ENGINEER
25501 west valley parkway
olathe ks 66061
direct 913 344.0036
fax 913 345.0617
Check out our new web-site @ www.smithboucher.com
From: equest-users-bounces at lists.onebuilding.org
[mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of
Mohammad Almasri
Sent: Wednesday, October 13, 2010 5:07 AM
To: eQUEST-users at onebuilding.org
Subject: [Equest-users] Different operation schedules for ventilation
system
Dear All,
Is it allowable ,based on the ASHRAE appendix G and LEED NC, for exhaust
fans in the non conditioned areas to operate with a schedule different
from the baseline schedule? I have a jet and exhaust fans for non
conditioned area , but those fans will operate in accordance to a
programmable timer (on-off).
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20101013/1ce7d738/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 1459 bytes
Desc: image001.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20101013/1ce7d738/attachment.jpeg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 16158 bytes
Desc: image002.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20101013/1ce7d738/attachment-0001.jpeg>
More information about the Equest-users
mailing list