[Equest-users] Project Runs
Peter Hillermann
e190984026 at exchange.1and1.com
Mon Jun 7 14:56:01 PDT 2010
To All,
How do I set up my "efficient" project run once I have created my ASHRAE
compliant baseline building model? I am currently working in detail mode.
Can this only be done from the wizard? I guess the better question is how do
I set up "RUN 2" in the model I've just built with different wall, HVAC etc.
inputs.
My current experience with project runs is GBS does eQuest work the same
since the DOE-2 engine powers them both?
Thanks,
PETER HILLERMANN
<mailto:peterh at westallarchitects.com> peterh at westallarchitects.com
westall
architects
3404 pierce drive
chamblee, georgia 30341
o 770.458.4113
f 770.458.5352
c 678.898.2936
westallarchitects.com
e-signatureUSGBC-Logo
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100607/11b7f2f7/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/gif
Size: 2436 bytes
Desc: not available
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100607/11b7f2f7/attachment.gif>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 3222 bytes
Desc: not available
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100607/11b7f2f7/attachment.jpeg>
More information about the Equest-users
mailing list