We did 3 project with this credit, we adjust the simulation (EE4 using
DOE2.1E) schedule, plug load, and weather and compare BEPS report and
monthly consumption with mesured data on specific load(loighting, fans,
chiller, boiler, pump, etc...)<br><br>
Martin <br><br>
<br><br>
At 12:20 18/05/2011, Jeremy Poling wrote:<br>
<blockquote type=cite class=cite cite="">Content-Class:
urn:content-classes:message<br>
Content-Type: multipart/related;<br>
<x-tab>        </x-tab>
boundary="----_=_NextPart_001_01CC1577.8257366F";<br>
<x-tab>        </x-tab>
type="multipart/alternative"<br><br>
Also, ASHRAE Guideline 14 covers Measurement and Verification as
well.  I have heard from others that they setup M&V plans based
on a combination of ASHRAE Guideline 14 and IPMVP, where IPMVP specifies
the broader goals and ASHRAE Guideline 14 specifies the specific
methods.<br>
 <br>
<b>Jeremy R. Poling, PE, LEED AP+BDC</b><br>
Manager | Sustainability Services<br><br>
TRANSWESTERN<br>
234 W. Florida St.<br>
Milwaukee, WI  53204<br><br>
Phone 414.255.3322 | Fax 414.224.7780 | Mobile 414.426.7273<br>
<a href="mailto:Jeremy.Poling@Transwestern.net">
Jeremy.Poling@Transwestern.net</a><br>
<a href="http://www.transwestern.net/Energy-Sustainability.asp" eudora="autourl">
http://www.transwestern.net/Energy-Sustainability.asp</a><br>
 <br>
 <br>
<img src="cid:7.1.0.9.2.20110518235504.0086ae20@mra.qc.ca.1" width=437 height=79 alt="http://www.transwestern.net/TWGreen.gif">
<br>
 <br>
 <br>
 <br>
<b>From:</b> bldg-sim-bounces@lists.onebuilding.org
[<a href="mailto:bldg-sim-bounces@lists.onebuilding.org" eudora="autourl">
mailto:bldg-sim-bounces@lists.onebuilding.org</a>] <b>On Behalf Of
</b>Marcus Sheffer<br>
<b>Sent:</b> Wednesday, May 18, 2011 10:50 AM<br>
<b>To:</b> 'Will Mak'; bldg-sim@lists.onebuilding.org<br>
<b>Subject:</b> Re: [Bldg-sim] LEED Measurement & Verification
Credits<br>
 <br>
There is some guidance here -
<a href="http://www1.eere.energy.gov/femp/pdfs/mv_guidelines.pdf">
http://www1.eere.energy.gov/femp/pdfs/mv_guidelines.pdf</a>  This is
the latest (v3.0) of the FEMP M&V Guidelines.<br>
 <br>
We have used Chapter 25 of the prior version (2.2) of this document as
simulation calibration guidance.  It is attached.<br>
 <br>
Marcus Sheffer<br>
Energy Opportunities, Inc/a 7group Company<br>
1200 E Camping Area Road, Wellsville, PA  17365<br>
717-292-2636,
<a href="mailto:sheffer@sevengroup.com">sheffer@sevengroup.com</a><br>
<a href="http://www.sevengroup.com/" eudora="autourl">
www.sevengroup.com</a><br>
 <br>
<b>From:</b> bldg-sim-bounces@lists.onebuilding.org
[<a href="mailto:bldg-sim-bounces@lists.onebuilding.org" eudora="autourl">
mailto:bldg-sim-bounces@lists.onebuilding.org</a>] <b>On Behalf Of
</b>Will Mak<br>
<b>Sent:</b> Wednesday, May 18, 2011 11:37 AM<br>
<b>To:</b> bldg-sim@lists.onebuilding.org<br>
<b>Subject:</b> [Bldg-sim] LEED Measurement & Verification
Credits<br>
 <br>
Hello all,<br>
 <br>
I was wondering if anyone has had experience with the LEED M&V
credit, specifically on New Construction? I looked back on old
discussions about this and basically it came down to reading over the
IPMVP Volume 3 Option D. However, I feel the language in the document is
vague and wondered if any of you out there have successfully completed
the credit for LEED and what the process is to “calibrate an energy
model”.<br>
 <br>
Are we talking about ensuring that the control system on the project can
generate data on the follow:<br>
 <br>
·         Weather Data<br>
·         Schedules<br>
o    Occupancy<br>
o    Equipment<br>
o    Lighting<br>
o    Temperatures<br>
·         Equipment operating
curves<br>
·         Utility bill rates<br>
 <br>
Other than the information above, I’m having a hard time understanding
what else you can modify on an energy model to try to reflect what is
actually happening post occupancy. (at least from an eQuest
standpoint).<br>
 <br>
Any suggestions? Thanks!<br>
 <br>
<b>William Mak, LEED AP BD+C</b><br>
Mechanical Design Engineer<br><br>
<b>EPSTEIN</b><br>
Architecture<br>
Interiors<br>
Engineering<br>
Construction<br><br>
600 West Fulton Street<br>
Chicago, Illinois 60661-1259<br><br>
D: (312) 429-8116<br>
F: (312) 429-8800<br>
E:
<a href="mailto:wmak@epsteinglobal.com">wmak@epsteinglobal.com</a><br>
W:
<a href="http://www.epsteinglobal.com/">www.epsteinglobal.com</a><br><br>
þ Epstein is a firm believer in sustainability. We ask that you please
consider the environment before printing this e-mail.<br>
 <br><br>
<br>
_______________________________________________<br>
Bldg-sim mailing list<br>
<a href="http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org" eudora="autourl">
http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org</a><br>
To unsubscribe from this mailing list send  a blank message to
BLDG-SIM-UNSUBSCRIBE@ONEBUILDING.ORG</blockquote>
<x-sigsep><p></x-sigsep>
<hr>
<br>
Martin Roy, ing. PA LEED®, président<br>
Martin Roy et associés<br>
1805 chemin Oka, <br>
Deux-Montagnes, Qc<br>
J7R 1N3<br><br>
<br>
Tel: 450-623-0340<br>
Cell. 514-594-6352<br><br>
<a href="http://www.mra.qc.ca/" eudora="autourl">www.mra.qc.ca<br><br>
<br><br>
<br><br>
<br>
</a><b>Message de confidentialité <br>
</b>Ce courriel (de même que les fichiers joints) est strictement réservé
à l'usage de la personne ou de l'entité à qui il est adressé et peut
contenir de l'information privilégiée et confidentielle. Toute
divulgation, distribution ou copie de ce courriel est strictement
prohibée et peut être l’objet de poursuites judiciaires. Si vous avez
reçu ce courriel par erreur, veuillez nous en aviser  et le
supprimer de votre système informatique sans l'imprimer, le copier ou le
faire suivre a quiconque. <br><br>
<b>Devez-vous vraiment imprimer ce courriel ?  Pensons
environnement...<br>
</b></body>
</html>