<table cellspacing="0" cellpadding="0" border="0" ><tr><td valign="top" style="font: inherit;">Hello,<br><br>Our client is occupying the 8th floor of a G+8 building. The central 
plant is a combination of Air cooled and water cooled chillers. The 
conditioned area of the project area alone is 45,000 sqft and segment 
area is 322,000 sqft. I simulated using the project area-segment area 
method. I used the existing conditions for segment area in both base 
case and proposed case. I modeled the project area as per ASHRAE 90.1 
2007. Now the problem is with the savings calculation. As per LEED, the 
formula is (Base case-Proposed Case)/(Base case*(project area/segment 
area)). Since the project is occupying only 1 floor, the project area/ 
segment area ratio comes up to 0.139 and because of this the savings 
goes higher than 100%. In other words, we will be multiplying the 
savings by 7 times, if we calculate the savings by the usual formula, 
(Base case- Proposed case)/base case. Kindly guide how to proceed. Thank
 you.<br><br>Regards,<br>Rathnashree<br></td></tr></table><br>