<DIV><FONT face=Arial size=2>I am modeling a new building applying for LEED
certification and want to make sure I'm using the right Appendix G baseline HVAC
system configuration. The proposed design has three gas/electric rooftop
packaged HVAC units, each with VVT dampers for subzoning, 6 to 12 subzones
per system, all zones are defined at the stage of design development we're at. I
believe I need Appendix G system type 3, gas/electric single zone units for my
baseline, but do I use the same three HVAC unit configuration and
assign the same eQUEST spaces/zones to the corresponding systems, or
do I use a separate HVAC system for each space/zone? Thanks in advance for
any replies.</FONT></DIV>