<!DOCTYPE HTML PUBLIC "-//W3C//DTD HTML 4.0 Transitional//EN">
<HTML><HEAD>
<META http-equiv=Content-Type content="text/html; charset=iso-8859-1">
<META content="MSHTML 6.00.6000.16705" name=GENERATOR>
<STYLE></STYLE>
</HEAD>
<BODY bgColor=#ffffff>
<DIV><FONT face=Arial size=2>I am modeling a new building applying for LEED 
certification and want to make sure I'm using the right Appendix G baseline HVAC 
system configuration. The proposed design has three gas/electric rooftop 
packaged HVAC units, each with VVT dampers for subzoning, 6 to 12 subzones 
per system, all zones are defined at the stage of design development we're at. I 
believe I need Appendix G system type 3, gas/electric single zone units for my 
baseline, but do I use the same three HVAC unit configuration and 
assign the same eQUEST spaces/zones to the corresponding systems, or 
do I use a separate HVAC system for each space/zone? Thanks in advance for 
any replies.</FONT></DIV>
<DIV><FONT face=Arial size=2></FONT> </DIV>
<DIV><FONT face=Arial size=2>Rick Routh</FONT></DIV>
<DIV><FONT face=Arial size=2></FONT> </DIV></BODY></HTML>