Hi All,<br><br>I'm working on a system where a geothermal loop and a cooling tower both supply cooling to a WSHP loop.  I am trying to control the loop so that cooling load goes first to the geothermal loop and second to the cooling tower as the ground loop will not be sufficient to provide cooling year-round.<br>
<br>I have run up against some funny things.<br><br>1.  If I let the program auto-size the cooling tower and use it's default control, I get a negative number for heat rejection energy (the cooling tower is given a capacity of -10 MBTU/hr with fan energy listed at -41 kw)<br>
<br>2.  If I size the cooling tower according to design at 4.2 MBTU/hr, the entire program shuts down<br><br>3.  If I try to run the model without the cooling tower, the entire program shuts down<br><br>Any thoughts?<br><br>
Thank You,<br><br>--<br>Karen<br><br>