<DIV><SPAN class=850591515-13102003>eQUEST would allow you to quickly build
buildings using the Schematic Design Wizard. The Schematic Design Wizard
has good defaults for many building types. Depending on the accuracy you
want initially, you could build one large building very quickly or you could
build several models of future buildings and import them all into a single model
for the central plant analysis. This second option would also allow you to
update the model as further information became available.</SPAN></DIV>
<DIV><SPAN class=850591515-13102003></SPAN> </DIV>
<DIV><SPAN class=850591515-13102003>If you have the first phase ready to model,
you could do that with a multiplier, or add Schematic Design models of future
buildings.</SPAN></DIV>
<DIV><SPAN class=850591515-13102003></SPAN> </DIV>
<DIV><SPAN class=850591515-13102003>Mike</SPAN></DIV>
<DIV><SPAN class=850591515-13102003></SPAN> </DIV>
<DIV><SPAN class=850591515-13102003></SPAN> </DIV>
<BLOCKQUOTE dir=ltr style="MARGIN-RIGHT: 0px">
<DIV class=OutlookMessageHeader dir=ltr align=left><FONT face=Tahoma
size=2>-----Original Message-----<BR><B>From:</B> postman@gard.com
[mailto:postman@gard.com]<B>On Behalf Of </B>Brian Thornton<BR><B>Sent:</B>
Monday, October 13, 2003 9:09 AM<BR><B>To:</B>
bldg-sim@gard.com<BR><B>Subject:</B> [bldg-sim] Looking for central plant
energy trade-off tool for conceptual de sign<BR><BR></FONT></DIV>
<P><FONT face=Arial size=2>Hello,</FONT> </P>
<P><FONT face=Arial size=2>Can anyone recommend software that allows fairly
rapid analysis of energy trade-offs between central plant equipment and
configurations, when the buildings to be served and loads are still
speculative? This is for a campus that will be built in phases over many
years, and most buildings are only loosely defined. DOE-2 will be more
difficult and detailed than warranted. </FONT></P>
<P><FONT face=Arial size=2>Thank you for your input.</FONT> </P>
<P><FONT face=Arial size=2>Brian Thornton, P.E.</FONT> <BR><FONT face=Arial
size=2>Lead Engineer, Energy Services</FONT> <BR><U><B><I><FONT
face="Arial Black" size=5>GLUMAC</FONT></I></B></U> <BR><B><FONT face=Arial
size=1>I N T E R N A T I O N A L</FONT></B> <BR><FONT face=Arial size=2>320 SW
Washington, Suite 200</FONT> <BR><FONT face=Arial size=2>Portland, Oregon
97204</FONT> </P>
<P><FONT face=Arial size=2>503.227.5280 Phone </FONT><BR><FONT
face=Arial size=2>503.274.7674 Fax</FONT> </P><PRE>
==================
You received this e-mail because you are subscribed
to the BLDG-SIM@GARD.COM mailing list. To unsubscribe
from this mailing list send a blank message to
BLDG-SIM-UNSUBSCRIBE@GARD.COM
</PRE></BLOCKQUOTE><PRE>
===========================
You received this e-mail because you are subscribed