[Bldg-sim] FW: FW: [BLDG-SIM] 90.1-2004 Appendix GGlazingforBaselinecase
Fred Porter
FPorter at archenergy.com
Mon Jan 28 08:51:32 PST 2008
The location of the document with this important modification may seem simple from the link. However the location is not at all obvious on the USGBC's "improved" website. On the LEED/LEED Rating Systems/LEED NC page, there is a link to a summary of our dear rating system, some posted errata, multi-building/campus guidelines, and a link to "Green Source Mag." A user would be forgiven if they thought this was a complete accounting of the system.
BUT, separately there is a LEED/LEED Resources (different than "Resources")/LEED Reference Documents page, where this memo resides along with the errata again. Nothing on the Rating Systems page indicates or links to this other page where this and some other important guidelines for EAc1 are located. This page should be linked to the rating systems page(s).
The CIR page, obscurely located under "Project Certification," should also be linked to the rating system summary page(s). And the CIRs should be viewable by the public not just us members.
Happy Monday
Fred Porter
AEC
>>> "Marcus Sheffer" <sheffer at sevengroup.com> 1/28/2008 9:02 AM >>>
Also refer to the memo posted on USGBC web site which allows the use of addenda to 90.1-2004. See link below.
http://www.usgbc.org/ShowFile.aspx?DocumentID=2664
Marcus Sheffer
Energy Opportunities, Inc/a 7group Company
1200 E Camping Area Road, Wellsville, PA 17365
717-292-2636, sheffer at sevengroup.com
www.sevengroup.com
From: bldg-sim-bounces at lists.onebuilding.org [mailto:bldg-sim-bounces at lists.onebuilding.org] On Behalf Of Keith Swartz
Sent: Monday, January 28, 2008 11:00 AM
To: bldg-sim at lists.onebuilding.org
Subject: [AVG SPAM] [Bldg-sim] FW: FW: [BLDG-SIM] 90.1-2004 Appendix GGlazingforBaselinecase
The text in the LEED-NC 2.2 Reference Guide for EA Credit 1 (page 173) states, “Demonstrate a percentage of improvement in the proposed building performance rating compared to the baseline building performance rating per ASHRAE/IESNA Standard 90.1-2004 (without amendments)…”
Sincerely,
Keith Swartz, PE, LEED® AP
Energy Center of Wisconsin
455 Science Drive
Suite 200
Madison, WI 53711
Phone: 608-238-8276 ext. 123
Fax: 608-238-0523
www.ecw.org
The Energy Center of Wisconsin is an independent, non-profit organization that seeks solutions to energy challenges.
From: Rishabh Kasliwal [mailto:RKasliwal at cogentenergy.com]
Sent: Friday, January 25, 2008 3:12 PM
To: Andrew Craig; Zoeteman, Mark R.; Bldg-Sim
Subject: Re: [Bldg-sim] FW: [BLDG-SIM] 90.1-2004 Appendix G GlazingforBaselinecase
Has LEED NC 2.2 adopted the Std. 90.1-2004 with the addenda OR have they just adopted the base standard?
Thanks,
Rishabh
From: bldg-sim-bounces at lists.onebuilding.org [mailto:bldg-sim-bounces at lists.onebuilding.org] On Behalf Of Andrew Craig
Sent: Friday, January 25, 2008 12:57 PM
To: Zoeteman, Mark R.; Bldg-Sim
Subject: Re: [Bldg-sim] FW: [BLDG-SIM] 90.1-2004 Appendix G Glazing forBaselinecase
Mark---
The change occurred in addendum a to 90.1-2004. Here is the text:
Andrew Craig, EIT,LEED AP/ Mechanical Designer
INTERFACE ENGINEERING
direct 503.382.2696
-----Original Message-----
From: bldg-sim-bounces at lists.onebuilding.org [mailto:bldg-sim-bounces at lists.onebuilding.org] On Behalf Of Zoeteman, Mark R.
Sent: Friday, January 25, 2008 12:44 PM
To: Bldg-Sim
Subject: [Bldg-sim] FW: [BLDG-SIM] 90.1-2004 Appendix G Glazing for Baselinecase
I've reviewed all the 90.1-2004 addenda and don't see where vertical
fenestration requirement of "distributing uniformly in horizontal bands
across the four orientations" has been removed. Addenda "as" which
refers to this section doesn't remove either.
Mark Zoeteman, FTC&H
-----Original Message-----
From: Zoeteman, Mark R.
Sent: Friday, January 25, 2008 3:40 PM
To: 'Michael.Rosenberg at state.or.us'; BLDG-SIM at gard.com
Subject: RE: [BLDG-SIM] 90.1-2004 Appendix G Glazing for Baseline case
-----Original Message-----
From: BLDG-SIM at gard.com [mailto:BLDG-SIM at gard.com] On Behalf Of Michael
Rosenberg
Sent: Wednesday, May 16, 2007 1:47 PM
To: BLDG-SIM at gard.com
Subject: [BLDG-SIM] 90.1-2004 Appendix G Glazing for Baseline case
The requirement to distribute fenestration uniformly in horizontal
bands across the four orientations has been removed from Appendix G in
the published Addenda Supplement to 90.1, 2004. See the ASHRAE website
for the supplement.
http://www.ashrae.org/technology/page/132
Michael Rosenberg
Oregon Department of Energy
625 Marion St. N.E.
Salem, OR 97301-3742
Phone : (503) 373-7809
Fax: (503) 373-7806
>>> Chris Jones <cj at cr-jay.ca> 5/16/2007 9:56:02 AM >>>
Appendix G notes that for the Baseline building: "Vertical fenestration
areas for new buildings and additions shall equal that in the proposed
design or 40% of gross above grade wall area, whichever is smaller, and
shall be distributed uniformly in horizontal bands across the four
orientations."
Does this mean that the Baseline building gets windows on all walls on
each orientation whether or not the Design case has a window in all
walls on each orientation. For example, if the west orientation has 30%
glazing overall but many spaces have no windows - some walls on the west
face have more that 30%. Do those spaces in the Baseline case get 30%
glazing? Or do I only put windows in the Baseline case where there are
windows in the Design case.
Thanks for any help!
Chris Jones, P.Eng.
14 Oneida Avenue
Toronto, ON M5J2E3
Tel. 416 203-7465
Fax. 416 946-1005
======================================================
You received this e-mail because you are subscribed to the
BLDG-SIM at GARD.COM mailing list. To unsubscribe from this mailing list
send a blank message to BLDG-SIM-UNSUBSCRIBE at GARD.COM
======================================================
You received this e-mail because you are subscribed to the
BLDG-SIM at GARD.COM mailing list. To unsubscribe from this mailing list
send a blank message to BLDG-SIM-UNSUBSCRIBE at GARD.COM
_______________________________________________
Bldg-sim mailing list
Bldg-sim at lists.onebuilding.org
http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20080128/c43c8a40/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 40818 bytes
Desc: not available
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20080128/c43c8a40/attachment.jpeg>