[Bldg-rate] Process Load Points Allowance

Sunny Side Up - John Beeson emailme0617 at yahoo.com
Fri Dec 4 12:20:52 PST 2009


Kevin,

Have you posted this question to LEEDUser?  (www.leeduser.com)




----------------------------------------------------------------------

Message: 1
Date: Fri, 4 Dec 2009 09:25:44 -0500
Subject: [Bldg-rate] Process Load Points Allowance

At USGBC.org, a CIR submitted 5/26/09 approvingly says that now projects are eligible to claim more than 4 points EA1 Credit through process energy efficiency savings and references a date 10/15/09.  I am unable to find any document with this date.
Is this notice posted somewhere other than the CIR page?
What is the new maximum EA1 point eligibility for process energy efficiency savings?

**************************



      
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-rate-onebuilding.org/attachments/20091204/27528578/attachment-0013.htm>


More information about the Bldg-rate mailing list