Hi All:
I'm modeling a plant that is manually changed over from heating to
cooling, and I'm wondering the best way to model this. Is this done in
the systems annual heat and cool schedules, or can this be done with
annual schedules for the Water-Side equipment? Do I need to create a
new ON/OFF schedule, and if so how do I link it to the boilers and
chillers?
I'm in detailed edit mode, and have a feeling this is a simple task, but
just can't figure out how.
thanks,
Nick Couture, LEED AP
Mechanical Engineer
3555 Veteran's Memorial Highway, Suite M
Ronkonkoma, NY 11779
Tel: 631.981.3990 ext. 230
Fax: 631.981.3971
ncouture at emtec-engineers.com
www.emtec-engineers.com <http://www.emtec-engineers.com/>
This message is intended only for the personal and confidential use of
the designated recipient(s) named above. This is not in anyway an
official statement of Emtec Consultants or solicitation to buy our
services. Emtec Consultants does not guarantee this Email transmission
to be secure or error-free. Any reproduction or changes to our drawings
and files without the consent of Emtec Consultants is strictly
prohibited.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100320/100493da/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 26315 bytes
Desc: email sig.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100320/100493da/attachment.jpeg>
More information about the Equest-users
mailing list