I've got an eQUEST model where my designed building has PIUs. I was
getting a number of hours of unmet loads till I turned on Night cycle
control. With PIUs you can set it to Zone fans only - which makes sense.
The loads were met and the energy usage went up marginally. 

 

The base building is a standard VAV system (system 7).  Since the VAV
system doesn't have zone fans, I have to set it to cycle on any. The
energy use goes up considerably in this case. Is this normal? Should I
be meeting the loads in another way?

 

Also - is it acceptable to have night cycling for a LEED/Appendix G
submittal? The building is just not meeting its heating needs if I don't
do this. It's a historic building with a lot of perimeter glass (single
pane) and so the perimeter zones get pretty cold at night (one of the
reasons we have PIUs) 

 

Am I correct in taking credit for this?

Vikram Sami, LEED AP 
Direct Phone 404-253-1466 | Direct Fax 404-253-1366 

LORD, AECK & SARGENT ARCHITECTURE
1201 Peachtree Street NE, Suite 300, Atlanta, GA 30361 
Responsive Design * Technological Expertise * Exceptional Service 
Please visit our new website | www.lordaecksargent.com
<file:///\\www.lordaecksargent.com\> 

P Think GREEN before you print.

 

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100305/2334e312/attachment.htm>


More information about the Equest-users mailing list