[Equest-users] BDL Error
Martz, Amanda
amartz at klingstubbins.com
Thu Jul 22 14:01:45 PDT 2010
Did you create a rate block, and then assign that block to a utility?
What did you input into the block?
When you go into your "custom elec rate," you should have the cost
either plugged into the energy/demand tab, or under the blocks tab. I
usually assign ratchets to individual blocks under "block charges" and
then assign these blocks to the electric utility.
________________________________
From: equest-users-bounces at lists.onebuilding.org
[mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of
mikef at facilitymgt.com
Sent: Thursday, July 22, 2010 4:46 PM
To: equest-users at lists.onebuilding.org
Subject: [Equest-users] BDL Error
I have set up rats for the local utility but when I use it I get an
error message. What I have used is
BLOCKS-ARE = INCREMENTAL
I get a BDL ERROR that says "Unknown Keyword or Previous .. Missing
How do I fix this? All of the information I have says for incremental
rates to use this, but if it is unknown what should I use?
Thanks
Mike Freeman PE.
Facility Management & Engineering, Inc.
-------------- next part --------------