[Equest-users] Simulation with Baseline model, Thanks for Your Advice. I am unable to figure it out.
Demba Ndiaye
Demba.Ndiaye at setty.com
Thu Jul 22 06:17:09 PDT 2010
eQuest uses "Baseline" to refer to your base model, with EEMs in mind. The word has actually nothing to do with either 90.1 or T24.
For example, if you are doing a LEED model and create two models: one proposed and one LEED baseline. Both will be called "Baseline" by eQuest.
_______________
Demba NDIAYE
From: equest-users-bounces at lists.onebuilding.org [mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of Guoguang Le
Sent: Wednesday, July 21, 2010 10:09 PM
To: equest-users at lists.onebuilding.org
Subject: [Equest-users] Simulation with Baseline model, Thanks for Your Advice. I am unable to figure it out.
To eQuest Expert,
I have a question to beg your answer. For an equest model, after I input some data and then run simulation, the report showed "baseline". What does this "baseline" mean? Is it meaning min requirement by Ashrae 90.1, T24, based on what I just input data or something else? In other words, how to run baseline model by using eQuest?
I appreciate your time very much! Thanks Lot!!!
Best regards,
James Le
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100722/1f204a03/attachment.htm>
More information about the Equest-users
mailing list