As long as rest of the model looks good, i.e reasonable unmet hours, I
always ignore this warning.
-Rohini
On 7/8/10, Jansen, Connor <Connor.Jansen at wspfk.com> wrote:
> Hello,
>
>
>
> I was wondering if anyone is familiar with this warning message:
>
>
>
> **WARNING***************************************************************
> *******
>
> Zone: Exam Room Zn could not
> successfully
>
> allocate all equipment energy to the 5-minute bins
>
> because of an equipment overload. The peak load
>
> used in ECONOMICS will not include the fraction due
>
> to the overload, but the PLANT reports will.
>
> Mon/Day/Hour: 2 2 8 Energy: 2.2 Unallocated: 0.596
>
>
>
>
>
>
>
> The only major change that created this error was switching from a PIU
> to a Packaged VAV serving multiple zones. This same error is occurring
> on several of the zones. Is there something I may have missed?
>
>
>
> Thanks for the insight.
>
>
>
> Regards,
>
>
>
> Connor
>
>
>
>
>
>