Hello,

 

I'm modeling a system that consists of a packaged VAV w/HW reheat for my
baseline model. I am currently over-sizing the systems per 90.1. I
oversized the cooling capacity using the "Cool Sizing Ratio" in detailed
edit but I am unable to figure out an "easy" way to oversize the heating
capacity. This option does not show up for heating at the AHU or zone
level.

 

Can someone enlighten me on how to oversize my heating capacity by 25%.

 