I think the capacities of boiler is sized based on non-coincident condition as default.

Min-Hwan Yang, LEED AP
Mechanical Engineer | yangm at kjww.com

200 West Jackson Boulevard, Suite 1200 | Chicago, Illinois 60606
312-294-0501 | Direct: 312-356-3750 | Fax: 312-294-0003
www.kjww.com


I have had the same problem when I let EQUEST automatically size the boiler for me.  In my situation, EQUEST drastically oversized the boiler so it was running at 10% capacity 90% of the time.  You can check to see if you have the same problem by looking at report PS-C to see what part load range your boiler is operating at.  To fix the problem, first I manually set the capacity of the boiler, which helped a lot, but the program was still over estimating the energy consumption.  Then, I created a custom performance curve using actual data for my boiler.  That solved my problem.

From: Josh Doherty [mailto:jdoherty at dcengineering.net] 
Sent: Tuesday, June 16, 2009 10:14 AM
To: equest-users at lists.onebuilding.org
Subject: [Equest-users] High boiler energy use compared to HW loop demand

I have a situation where my boiler energy use (= 950 MBtu) is extremely high compared to the hot water loop demand = 550 MBtu.  The modeled efficiency of the boiler is 80%...which should result in an estimated 690 MBtu of boiler energy use.  Any ideas what could be going on here?  Thanks.

Josh Doherty

This message and any attachments contain information intended for a specific party and may include sensitive or confidential material. If you are not the intended recipient, please do not read, copy, use, or disclose to others.  Please notify the sender of the delivery error by reply and then permanently delete this message and all attachments.