[Equest-users] VAV system unmet hours
Brett M. West
bwest at rmf.com
Wed Aug 26 12:55:07 PDT 2009
I am modeling a system which consists of rooftop AHU's that serve
multiple VAV boxes in a classroom/office building. The AHU's are served
by chilled water and hot water loops for conditioning. The problem I am
having is that the systems are coming up in the SS-R report as having
large amounts of unmet hours. Even if I try to manually add heating to
the systems there is no affect on the hours. I have attached the pd2 and
inp files. Any suggestions would be appreciated. Thanks
Brett M. West
Design Engineer-Mechanical
RMF Engineering, Inc.
T: 843-971-9639 ext. 1499
F: 843-971-9641
bwest at rmf.com <mailto:bwest at rmf.com>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20090826/911f4c72/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: PROPOSED_8_26_OAtransfer.pd2
Type: application/octet-stream
Size: 130984 bytes
Desc: PROPOSED_8_26_OAtransfer.pd2
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20090826/911f4c72/attachment.obj>
More information about the Equest-users
mailing list